New Projects

The Technical Specifications and The Bid Proposal will be drafted by the Engineer and given to the Secretary to be typed. The "Front-End" of the Specifications will be put together by the secretary. The Engineer will tell you a previous job to use as an example. The following file folders should be made at this time:

  1. Master File - (Green Letter Size) Labeled with Job Number and Project Title
  2. Bid File - (Red Legal Size) Label with Job Number and Project Title
  3. Agency File - (Blue Legal Size) Label with Job Number, Project Title and specify what agency is funding the project.

Correct Way to Type Technical Specifications#

**Title of Item**
I.
A.
1.
a.
(1)
(a)
(i)