When The Notice Of Award Comes Back Signed By The Owner
- Do the Letter of Award to the Contractor
- SEE FORM LEITER SECTION (Page 82 & 83)
- Determine the # of Contracts that are needed; Send this number of copies of the following to be executed by the Contractor:
- Contract Agreement;
- Performance Bond (The Performance & Payment Bond May Be Combined and Be The Performance-Payment Bond);
- Payment Bond
Also Send:
- Original Notice of Award (Contractor to sign the Acceptance) - Second Page
- General Conditions
- Highlight The Sections Concerning Insurance Requirements
- Supplemental General Conditions
- Highlight The Sections Concerning Insurance Requirements
Ask that the following items be executed and returned to us for binding in the contracts:
- Contract Agreements
- same # as # of contracts needed
- Performance Bonds
- same # as # of contracts needed
- Payment Bonds
- same# as# of contracts needed
- The Original Notice of Award
- Certificates of Insurance
- same # as # of contracts needed
- Letter Stating Specifications Have Been Met - If we don't get enough originals for each contract, put the original letter in the Owner's Contract
- Power of Attorney
- same # as # of contracts needed